TCM Project Performance
Bryan Bertrand & Greg Snyder
Cost Estimating Performance
| Project | Estimate | Low Bid | Delta | Bid Range |
|---|---|---|---|---|
|
MENDOTA JUVENILE TREATMENT CENTER EXPANSION MENDOTA MENTAL HEALTH INSTITUTE Madison, Wisconsin |
$52,364,000 | $53,223,000 | -1.6% | 4.5% |
|
STANLEY MUSEUM OF ART UNVERSITY OF IOWA Iowa City, Iowa
|
$36,542,000 | $35,750,000 | 2.2% | 10.8% |
|
KOHL CENTER ADDITION & REMODEL UNIVERSITY OF WISCONSIN Madison, Wisconsin |
$35,921,000 | $33,294,000 | 7.9% | 3.7% |
|
INVER GROVE HEIGHTS FIRE STATION #2 CITY OF INVER GROVE HEIGHTS Inver Grove Heights, Minnesota |
$7,940,000 | $8,194,000 | -3.1% | 9.3% |
|
MEDICAL EXAMINERS FACILITY HENNEPIN COUNTY FACILITY SERVICES Minnetonka, Minnesota |
$38,685,000 | $36,035,000 | 1.8% | 6.6% |
|
EASTERN NEBRASKA VETERANS HOME NEBRASKA HEALTH & HUMAN SERVICES SYSTEM Bellevue, Nebraska |
$15,367,400 | $15,286,000 | 0.5% | N/A |